House Project – The Good, Bad, Ugly – and Ugliest

We have officially started the last week of the house portion of the project. Our target was that the house itself would be completed by September 30 and that October would be reserved for issues outside the house: completion of the wall and spikes, completion of the shop, completion of the canal, etc. We “might” actually hit our target, so this looks like a good time to review the entire project and call out some of the problems I have only hinted at before.

The Good: The contractor that we eventually hired had an architect/engineer friend who came up with two modern designs, both of which we liked. We asked for elements from both designs which he combined to create a final design. We were excited.

The contractor came up with a bid which I thought was OK but maybe a bit high. He ultimately agreed that his bid would be a fixed price; meaning that there would be no cost increases from inflation. As you will soon see, this became irrelevant. Nonetheless the negotiations went well and soon we were signing a contract with a lawyer.

Not long after, the construction started. While I would hate to categorise the entire subsequent process as bad, this was the end of the honeymoon period.

The Bad: Our contractor hired a foreman and work commenced. We were soon to find out that the foreman was only hired for 2 days/week. We complained about that but the contractor assured us that between he and the foreman there would be plenty of supervision. There never was.

A small crew, averaging 6-8 began the wall (or fence as it’s called here) surrounding the property. Janet and I would come over daily to check the progress. Sometimes progress was being made and sometimes not so much. More complaints to the contractor, more assurances, and the wall progressed, though slowly.

Three months later the wall was mostly done and they switched to work on the house. The crew expanded to about 12-13. It was quickly clear to us that a crew of a dozen would take two years to finish the house. More complaints, more assurances but the crew was rarely large enough.

There were ups and downs, mistakes and more mistakes, but yet the house did begin to take shape. Within six months we could see that these guys might actually be capable of building this house; we really weren’t sure before. But by the six month mark, money became a worry.

The contractor’s money methodology was simple. He would ask for a certain sum of money monthly and I would give it to him. After a few months the pattern was set but I could do the math and confronted him, “At the rate you are asking for money, the money will run out before the house is completed.” He assured us the first few months were the larger portions of money required because of steel and concrete, etc. and that later requests would be smaller. This never turned out to be true.

As a certain point Janet and I had one of those “Come to Jesus” meetings with the contractor. Janet said, “We have given you half the budget but we only have 25% of a house.” He again reassured us, showing us the numbers of what was still left to buy and how much got paid to the crew and that we still had money to complete the project. I was skeptical. Similar conversations and similar assurances would occur monthly.

Janet would try to assure me. “We have a contract. We can sue him if he doesn’t finish.” As the more experienced and more cynical partner I told her “A contract is only good if the person you are suing has money to pay you.” Nonetheless since progress continued we remained cautiously optimistic.

As I have documented in other blog posts, not only was supervision of the crew hit and miss, so was material purchasing. The crew and foreman often complained to us about not having the materials they needed. We would complain to the contractor and eventually more materials would arrive. But this clearly slowed the project. And less efficiency meant more cost.

We tried to help the contractor save money. Whenever we would see a needed piece for the project on sale we would contact the contractor. “Robinsons has overhead fans on sale for a great price.” We would buy the sale items and minus that amount of money from what we owed the contractor. While this should have been his methodology all along (shopping for deals), in the end it didn’t help him.

We also tried to help the contractor schedule the job. In June we went to the contractor and told him we needed the house done by the end of September so that we could move in during October. He agreed that it could be done. He told the workers that if they finished by September 30 he would give them a lechon party. Lechon is very big in the Philippines and for a few weeks the crew was excited. Pretty soon they knew the truth; that there would be no lechon.

The Ugly:

And then the fateful day occurred (cue organ). The contractor asked to meet with us at our rental home, which he never did before. He explained that he had no more money and had used some of our money to buy himself a piece of property. He couldn’t sell the property because the title was not finalised and the economy was soft.

Frankly we already knew that he had purchased a piece of property. This is the Philippines and everyone knows everyone’s business and so we had been told months before that the contractor had bought a lot. At the time my attitude was, ‘Well he’s entitled to make a profit and if he uses some of his profit to buy a lot that’s his business, as long as I get my house.’ But now it was clear we were not going to get our house.

Our first step was to take over all purchasing for the project; we simply felt we could no longer give the contractor any more money. What was shocking was how little materials were at the project. The crew needed everything. I made a list of the major elements I knew still had to be purchased, but that list turned out to be a fraction of what they really needed. Janet and I were going to stores all day long every day and cash was flowing out of our bank faster than I could keep track of it. My desk had a stack of receipts which I tracked on my spreadsheet and soon it was official; the budget was spent and we were in the red.

Now they can buy kamagra online to make viagra no prescription uk treatment more enjoying. Vinpocetine also functions proactively to boost the norepinephrine levels as compared to cipla generic cialis other drugs. Then, the blood buy generic viagra you can look here circulation in the veins and arteries are getting lots of blood and then the stamina and vigor for copulation is increasing. Most M.D.s do not typically try to find the plastic surgery specheapest tadalafil online ts? That’s not a go-on-a-war challenges as described by many skeptics.

For the next few weeks we gave a modest amount to the contractor weekly to pay the crew. Then one day I was contacted by a guy who was also using our contractor. “Is your crew being completely paid? Mine isn’t and they are ready to quit.” I said, “I think they must be – no one’s complained.” The next day Janet and I went to the site and asked each crew member. BTW, by this point in time the crew was over 30. Every crewman was owed some money. One poor guy was owed back pay for three weeks.

At that point we took over the payroll and paid everyone everything they were owed. It was the equivalent of an extra week’s pay.

For all intents and purposes we took over the running of the project. We asked the foreman if he could temporarily work more days and he agreed. Janet spent 8 hours a day on site watching the crew and yelling at them; she does this well. I ran around daily buying stuff. We were and are busy busy retirees.

We brought in Janet’s oldest brother, Marlon from Cebu to work. He’s worked very hard and really shown some of the crew members how work is supposed to be done. This has turned out to be a good decision, although our little rental house is now a crowded little rental house.

While there have been plenty of glitches everyone can see that the crew has worked harder and gotten more done. With luck (fingers crossed) this week the final elements of the house will be done. On Saturday Janet is giving the crew the promised lechon party.

Next week the air conditioners get installed and the crew moves to the outside projects and shop completion. With even more luck those elements will be completed in October.

In the meantime we know that there are a hundred little touch up jobs required in the house, mostly involving paint. I will be finishing the doors and there are a lot of them. Janet plans to bring the kids up from Alcoy on their school break to clean. Only in the Philippines do kids get excited to come to an overcrowded rental house to be worked like dogs.

The Ugliest: I may be conning myself, but I pride myself in telling the truth. It may be my truth or my interpretation of the truth but still I tell the truth. I ran a business for 14 years and when problems occurred I told the customer the hard truth. I worked at Intel for 15 years and told my accounts (Fortune 500s all) the cold hard truth and they accepted it.

I have become angered and depressed by how often I have been lied to in this process. Sometimes the simple lies are lies of omission, sometimes the gentle lies of ‘we don’t want to admit there’s a real problem,’ but many times bald faced lies were told to my face. It was infuriating and at times deeply depressing. I have no conclusions and no interest in globalising my experience but when I say “two plus two is four” and am told “no it’s five” – well as I say it’s infuriating.

While I don’t have final figures yet it looks to me like we will end up 20% over budget. The contractor promises that when he sells or mortgages his property he will give us some money. It might happen but I’m not holding my breath. He’s actually not a bad guy but got in way over his head.

Conclusions: Assuming you still want to own a house in the Philippines after having read all these blog posts, here are my recommendations:

  1. Buy an existing house. There are plenty of “foreigner houses” for sale throughout the Philippines and often for good prices.
  2. If you must build your own dream house, function as your own contractor. Hire an engineer and or foreman to run the project, while you do the purchasing. You will spend a year or more of your life going crazy, but it is probably the safest way.
  3. Did I mention that you can buy an existing house here and let your wife remodel it?

A funny (in my warped way) story: We did know for months that our contractor was in financial trouble because he kept listing stuff for sale on FB Marketplace. Generally it was stuff I would have no interest in but a few weeks back he listed a high end Canon camera with a couple lenses; a model that would have been a professional model a few years back. I like photography but sold my Nikon gear before I moved here. BTW, when I worked at Intel there were practically fights in the hallways over the Nikon vs. Canon debate. Shows you what nerdy engineers will get excited about.

I sent him a message. “Why don’t you just give the camera to me, as part of what you owe me.” He agreed, but could I give him a little bit to pay off the last of the workers. I agreed. When Janet and I inspected the camera I asked, “How long have you owned this?” “Eight months,” was his reply. Janet and I caught each other’s eye. I knew I was basically getting back the camera I had paid for.

So, I don’t have a house yet but I do have a nice camera.

Why the Hell Would You Buy a Lot in the Philippines – PART 4

Part 1

Part 2

Part 3

So, now Janet and I (mostly Janet) own two lots in the Philippines. I can hear some of you mumbling, “they’re nuts,” and you would not be completely wrong.

While the lot in Southern Cebu was a very good deal, by the time Janet paid the taxes (the ones that were higher than expected) it had taken a chunk out of her savings for the project.

Janet researched house building here and really learned a lot. She must have drawn up 10 different versions of a potential house design. Occasionally I would say, “You know you could get everything you want and save money by reducing the overall size of the house.” And she did!

We went to her hometown and spoke to a couple of “architects” about drawing up blueprints; architect is a misnomer; mostly they just draw up the blueprints. A blueprint is a requirement to get a permit and while some people do not bother to get the required permits, Janet was determined to do it all right. But the reality that we found out is that the blueprint and associated cost estimates are a formality that might not be used much by the builder or foreman. The first architect we interviewed seemed competent but was expensive for a provincial town. We went with guy number two, since he was cheaper.

Now, how to build the house? You can hire a contractor and certainly that’s what we will do for our own home here in Valencia. But for a simple house in a provincial area, that just adds expense and we already weren’t positive whether we could afford to build the entire house.

So in the end we hired a Foreman and Janet functions as her own contractor. Here’s what that means. The Foreman, aka Boy, oversees the crew. He tells Janet every week what materials he needs. Janet purchases those materials and arranges to have them delivered to the job site. Unfortunately in her home town there are not a lot of options for where you can buy material, so she’s pretty much stuck with the vendor and whatever price is charged.
At the second place, it reminds us of the famous website of viagra generic discount the famous newspaper. These are rich in sildenafil levitra potassium, minerals, and other essential element to accomplish needs to full endurance needed in the bed. Gorilla as a Going Here buying viagra without prescription is committed to meet and exceed all standards outlined by leading pharmacy accreditation online. 5mg cialis tablets This is their way of seeing if you will leave.
Every Saturday Janet has to pay the crew for the week’s work. General laborers earn 250 pesos a day (about $5). Skilled labor (masons, electricians, plumbers) usually cost 400 pesos a day but Janet had Boy negotiate 350/day, based on the fact that the laborers would have consistent work. In the provinces often projects are done in fits and starts, but Janet was determined to go from beginning to end without let up. The Foreman earns 500P/day. He mostly oversees and does some labor. Our Foreman, Boy, seems quite competent. Janet had actually hired another Foreman, a cousin of hers, but just a few days before the building was to commence he took another Foreman job and bowed out. Fortunately Boy was available. And BTW, he’s a lot older than his name would imply; I’d guess close to my age.

In addition to the paid labor, Janet’s older brother works full time on the project. Her father works his farm during the day as usual and then goes to the job site and works till dark. Every weekend the kids go to the job site and help! It’s amazing to see and you can check out a brief video to see them all at work here.

At this point, at the beginning of August, the house is really coming along and if I had to venture an uneducated guess would say we are at least halfway finished. The foundation’s been done, the concrete floor has been poured, the walls are up and soon they’ll start working on the roof.

The workers, despite their modest pay, work very hard. Now they don’t necessarily work efficiently but they work hard and earn their money. When I say the work is not that efficient I mean that the basics are not there and are substituted with hard labor. There’s no wheelbarrow, for example. Almost nothing of what you’d call jigs and fixtures; things that in the West would be done for items that had to be repeated.

Everyone in the family is excited with the house. It reminds me of the last time I had any involvement with the building of a new house. I was 6 or 7 years old and my parents were building a house in the suburbs. Every weekend we’d go and check the progress. At first I thought it was all a big nothing but as the weeks went by and I saw my bedroom framed it all got very exciting. I would imagine that’s how they are all feeling now.

——————–

There’s no point in arguing with expats here who say they would never do what we are doing. I get it – really I do. Whether or not they like their girl’s family they have no interest in helping them in such  a way. Like I say I do get it. As the mantra goes, “they did fine before I came along, didn’t they?”

The truth is compared to Janet, I’ve done very little. Mostly I provided a stable environment where she could pursue her dream; a dream that her parents and family would have a decent home to live in; a home of their own. Maybe I also provided some guidance but I’m not even sure of that. After all Janet has a B.S. in Business and is quite capable of tracking the money, labor and supplies. Mostly I just look on and have people give me credit for what I mostly haven’t done. It’s a pretty good life!

 

Pillazo Family Building Their House

Here’s a short video of all of Janet’s It dilates the blood vessels and helps cialis pills canada to ensure more blood supply and cause firmer and fuller erection. What causes pathological disintegration in the first instance. price viagra In time of making an order purchasing viagra Read Full Report is very easy. This chemical leads for the damage of the PDE5 enzymes & pills viagra leads for the unblocking of the clogged routes of the male reproductive organ which is mainly blocked with the strong functioning of the PDE5 enzymes. family working on building the family home!

https://youtu.be/S-8is-Vr5Hg